Concrete Calculator
Work out how much concrete you need for a slab, round pier, column or steps. Get cubic yards, bags with a waste allowance and a cost estimate. Free.
About this tool
Ordering concrete is stressful when you do not know how much to buy: too little and the pour stops halfway, too much and you pay for waste. This free concrete calculator takes the guesswork out. Enter the size of your slab, round pier, column or steps and it works out the volume in cubic feet and cubic yards, then tells you how many bags you need for the bag size you pick — with a waste allowance built in, and a cost comparison between bags and ready-mix if you enter prices. It uses the standard bag volumes from the manufacturers' data sheets. There is nothing to install and no signup, and the result appears in seconds.
By Azhar Hussain · Last updated: 19 November 2026
How to use
Pick what you are pouring first: a rectangular slab or footing, a round slab, a round column or sonotube pier, or a flight of steps. Only the measurements for that shape are shown. Measure in feet for lengths and in inches for thickness, then pick your bag size: 80 pound bags are the most common for big jobs, while 40 pound bags are easier to carry. The waste allowance starts at 10 percent — change it to 5 for tidy forms or 15 for rough ground. Press Calculate Concrete to see the volume, the cubic yards and the number of bags, with the waste included. Add a price per bag or per cubic yard to compare the two ways of buying. The tool rounds bags up, because you cannot buy part of a bag.
The math behind it
Volume comes from length times width times thickness, with the thickness changed from inches to feet by dividing by 12. A slab 10 feet long, 10 feet wide and 4 inches thick is 10 times 10 times 0.333, which is 33.33 cubic feet. There are 27 cubic feet in a cubic yard, so that slab needs 1.23 cubic yards. Bag counts come from the volume each bag fills: an 80 pound bag fills 0.6 cubic feet, a 60 pound bag fills 0.45, a 50 pound bag fills 0.375 and a 40 pound bag fills 0.3. So the same slab needs 56 bags of 80 pound concrete, or 62 with the 10 percent waste allowance. A round column uses pi times the radius squared times the height, and steps are a solid pour: each step carries the full volume of every step above it.
The four shapes and their formulas
Every shape reduces to a volume in cubic feet, then to cubic yards by dividing by 27, because a cubic yard is 3 feet on each side.
| Shape | Formula (cubic feet) | Example |
|---|---|---|
| Rectangular slab or footing | Length × width × (thickness ÷ 12) | 10 × 10 ft, 4 in = 33.33 cu ft |
| Round slab | π × radius² × (thickness ÷ 12) | 6 ft dia, 4 in = 9.42 cu ft |
| Round column / sonotube | Count × π × radius² × height | 12 in dia, 4 ft deep = 3.14 cu ft each |
| Steps (solid pour) | Width × (tread ÷ 12) × (riser ÷ 12) × N(N+1) ÷ 2 | 4 steps, 3 ft wide = 15.00 cu ft |
A footing uses the same formula as a slab — it is just narrow and deep instead of wide and thin. A wall is entered the same way: length, height as the width, and thickness as the depth. Steps are the shape people most often underestimate, because the bottom step supports the full volume of every step above it.
Bag yields: how much one bag makes
These are the yields printed on the manufacturers' data sheets for standard concrete mix (Quikrete Concrete Mix No. 1101 and Sakrete's standard mix). Bags per cubic yard is just 27 divided by the yield.
| Bag size | Yield per bag | Bags per cubic yard | Best for |
|---|---|---|---|
| 80 lb | 0.60 cu ft | 45 | Slabs and driveways — cheapest per cubic foot |
| 60 lb | 0.45 cu ft | 60 | Walkways and solo work — the middle ground |
| 50 lb | 0.375 cu ft | 72 | Smaller jobs where 60 lb is too heavy |
| 40 lb | 0.30 cu ft | 90 | Small repairs, fence posts — easiest to carry |
Fast-setting, high-strength and specialty mixes yield differently — always use the figure printed on the bag you actually buy. And remember the yields allow nothing for waste: the manufacturers' figures assume a perfect pour on a perfect base, which no real job has.
Waste allowance: 5, 10 or 15 percent?
Order more than the exact volume. Spills, formwork that spreads slightly, an uneven subgrade and the concrete left in the chute or mixer all eat into the amount, and running short halfway through a pour is far more expensive than a spare bag. Ten percent is the standard allowance for most home projects. Use 5 percent for tidy ready-mix forms on a well-compacted base, and 15 percent for irregular shapes, sloped ground, a gravel subgrade that may have voids, or your first concrete project. The calculator applies the allowance before rounding bags up, so the bag count already includes it.
Bags or ready-mix?
The break-even point is roughly one cubic yard. One cubic yard needs 45 eighty-pound bags — that is 3,600 pounds of material to open, dump, mix and pour by hand. Under half a cubic yard (about 22 bags) bagged concrete is practical and cost-effective; above a yard, a ready-mix delivery or a rented mixer trailer is usually cheaper and far easier. Worked comparison: a 10 by 10 foot slab at 4 inches needs 62 bags of 80 lb mix with waste, about $401 at $6.47 a bag, against 1.36 cubic yards of ready-mix at about $190 at $140 a yard before delivery — bags cost about double here. A full ready-mix truck carries roughly 10 cubic yards, and most plants sell in quarter- or half-yard steps, so round your order up to the next step they offer. Enter your own prices in the calculator for a comparison on your job.
Worked examples
Patio slab, 10 × 10 ft at 4 in. 33.33 cubic feet, 1.23 cubic yards, 56 bags of 80 lb mix — or 62 bags with the 10 percent waste allowance (1.36 cubic yards). Bags are practical at this size, but ready-mix is cheaper.
Garage slab, 20 × 12 ft at 4 in. 80.00 cubic feet, 2.96 cubic yards, 134 bags — or 147 with waste. Firmly ready-mix territory: that is over two tonnes of bags.
Round patio, 6 ft diameter at 4 in. 9.42 cubic feet, 0.35 cubic yards, 16 bags of 80 lb mix. A small bag job.
Deck footings, twelve 12-inch sonotubes 4 ft deep. 3.14 cubic feet each, 37.70 cubic feet total, 1.40 cubic yards, 63 bags — or 70 with waste. A ready-mix short load or a mixing trailer beats hauling 70 bags.
Steps, 4 steps 3 ft wide with a 12-inch tread and 6-inch riser. 15.00 cubic feet, 0.56 cubic yards, 25 bags — or 28 with waste. Steps are the most commonly underestimated pour, because the lower steps carry the volume of everything above them.
Shed base, 12 × 10 ft at 4 in. 40.00 cubic feet, 44.00 with waste, 1.63 cubic yards, 74 bags of 80 lb mix.
Thickness and strength (PSI) guide
Thickness alone does not make a slab last — a compacted base, reinforcement, control joints and a proper cure matter just as much. Check your local code before pouring; the figures below are the usual residential guidance.
| Project | Thickness | Mix strength |
|---|---|---|
| Sidewalk, patio, walkway | 4 inches | 3,000 PSI |
| Shed base, garden path | 4 inches | 3,000 PSI |
| Driveway (cars) | 4–6 inches (5–6 recommended) | 3,500–4,000 PSI |
| Garage floor | 4–6 inches | 3,500–4,000 PSI |
| Driveway (trucks, RVs) | 6 inches minimum | 4,000–4,500 PSI |
| Footings and foundations | Project and code dependent | 3,000–4,000 PSI |
| Hot tub pad | 6 inches | 4,000 PSI |
The building code minimum for a slab on ground is 3.5 inches. A driveway in a freeze-thaw climate should use a 4,000 PSI mix with air entrainment, which protects against scaling from road salt.
Curing: when can I walk and drive on it?
Concrete gains strength gradually, and the timeline below assumes normal weather (about 65 to 75 °F) and a standard mix. Cold or hot weather moves every number.
| Milestone | When |
|---|---|
| Walk on it | 24 to 48 hours |
| Light furniture, grill | About 3 days |
| Park a passenger car | 7 days (about 70% of design strength) |
| Heavy trucks, RVs, loaded vehicles | 28 days |
| Full design strength | 28 days |
| Seal the slab | Not before 28 days |
Keep the slab moist for the first 7 days for the best results — drying too fast makes it brittle. Do not use de-icing salts on new concrete in its first winter.
Troubleshooting and method
Ran short mid-pour. The usual causes are an uneven subgrade (the base was deeper than measured in places), forms that spread, or no waste allowance. Measure the thickness in several places, not just one, and keep the 10 percent allowance. If you do run short, finish the section you are on and treat the rest as a second pour with a proper joint — never feather a thin patch over the edge.
Ordered far too much. Check the thickness first: an extra inch over a whole slab adds 25 percent to the volume at 4 inches. Measure again, and return unopened bags — most suppliers take them back.
Method. Volume = length × width × (thickness ÷ 12) for slabs, π × radius² × height for columns, and the solid-pour steps formula above. Cubic yards = cubic feet ÷ 27. Bags = ceil(cubic feet × (1 + waste%) ÷ yield per bag). All figures are planning estimates — confirm with your supplier and local code.
Sources. Bag yields from Quikrete Concrete Mix No. 1101 and Sakrete data sheets, checked November 2026 against CalculatingConcrete (updated 17 November 2026), HomeDIYOnline, NailTheMath, MeasureThenBuild, FixnFigure, Yardstickly, BulkMaterialCalculator and CalcTheJob. Shape formulas, waste guidance and the bags-vs-ready-mix break-even from MaterialWright, Construction Bros, CalculatorsHouse and OnlineConvers. Thickness, PSI and curing figures from the IRC, HammerCalculator, MyConcreteCalc, CJM Concrete, ProBuilderCalc and BuildCalcu.
Frequently asked questions
How many bags of concrete do I need?
How many cubic feet are in a cubic yard?
How thick should a concrete slab be?
Should I buy extra concrete?
What size concrete bag is best?
How much concrete do I need for a round column?
How do I calculate concrete for steps?
How many bags of concrete are in a cubic yard?
Should I use bags or order ready-mix?
How long does concrete take to cure?
What PSI concrete do I need?
What if my bag lists a different yield?
Related tools
Area Calculator
Volume Calculator
Surface Area Calculator
Cubic Feet Calculator
Circle Calculator
Perimeter Calculator
💬 Comments
Have a question about this page, or an idea to make it better? Share it below — your feedback helps everyone who uses this site.